![]() Our support covered carrying out cable and cable protection system installation using Global Dynamic Analysis tool, Orcaflex. Now completed, the wind farm exports 210 MW to the national grid. The project was part of the UK Round 2 Offshore Wind development that has seen the installation of 42.5km of 33kV cables. We were contracted to support Technip Offshore Wind Ltd (TOWL) in the installation of inter-array cables for the Westermost Rough development, located 8km off the Yorkshire coast. We also provided formal training to the TOWL team to support their future developments. ![]() Our methodology allowed for the winches to be accurately sized allowing the cables to be ‘flown in’ reducing possible damage. We provided Orcaflex analysis for Technip Offshore Wind Ltd to underpin and validate their installation procedure of the inter-array cables for the Westernmost Rough Development and ensure that cable damage was minimised.